Dear All,
Thank you for your comments and suggestions on the draft Consortium
Agreement, but I would like to point out that not all of them have been
included in the (hopefully) final clean version, which is attached to this
e-mail. I also attached the previous version, so you can compare them.
Some remarks:
- Section 7.1.1., last paragraph: We don't see the second part of the
sentence necessary for two reasons: The provisions of payment are detailed
in Section 7.3.1 and the same part of STAR I CA does not contain any more
either.
- Section 7.3: We modified the schedule plan slightly, the
pre-financing amount would be distributed in a proportion of
20%-40%-20%-10%-10%. The first payment would be made without delay after the
CA is signed by all of us, then the second payment would follow in December
2018, so by the end of this year already 60% of the pre-financing amount
would be distributed. If we would distribute the amount in 5 equal
instalments, the Partners would receive only 40% of the pre-financing amount
by the end of the year. We insist on this method and we hope you can accept
this it as well. You can find the payment schedule plan at the end of the CA
(Attachment 2).
- Section 8.2: Modified according to David's suggestion.
Please review the CA for the last time. Our President can sign the CA on
Thursday (he is out of office until then) and then we will send the document
to VUB by post.
Other:
- @ Everyone: If you have nominees for the External Advisory Board,
please give us their names and contacts a.s.a.p.
- @Everyone: Please give me your feedback on deliverable D1.1 (Minutes
from the KOM) until 27 September. It should have been uploaded until 31
August, but as it would of course not be possible, I made a comment in the
PP about the situation stating that the minutes will be uploaded a.s.a.p.
- @ István / Lina: Could you please urge your designer a little bit to
design the logo a.s.a.p. I would like to put the logo on D1.1.
Thank you.
Best,
Gábor
P.S. Photos from the KOM are enclosed as well.