Dear All!
We have discussed internally all possible scenarios concerning the
starting date of the STAR II project. Taking into account all
considerationsthe NAIH came to the conclusion that the project should be
started on 1 of August. We fully understand your concerns of the
holidays but we hope that the PO orin her absence a competent colleague
of her will be available during the greater part of the summer also so
the signiture of the grant agreement by the Commission can be received
on time. In light of the above mentioned the preparation of the grant
agreement can be started in July.
Please share your standpoint as soon as possible because if you all
accept 1 of August we immediately start the preparation of the GA in
order to send you the document for signiture. The GA will be sent to the
Trilateral first and than to the VUB in Brussels. Please check your
postal addresses given and inform us about any changes.
Furthermore we support István’s suggestion that the KoM should be held
in M2 in Budapest. We would like to organize the meeting on the 6-7 of
September. If the date is OK for you please confirm the date of the KoM.
Best regards,